SECONDHAND GIGAWATT-SCALE PRISMATIC BATTERY CELL TO PACK ASSEMBLY LINE
Rated Capacity: 1.5 GWH per Year
Installation Equipment Plant Conditions
SN Item Parameter
1 Power Supply 380V ±10%, 50Hz, ~100 kW
2 Air Source 0.5–0.8 MPa
3 Gas (Optional) Nitrogen 0.4–0.6 MPa, 99.99% purity
4 Floor Load ≥650 kg/m²
5 Environment 15–35°C, 40–85% RH
6 Others No vibration, dust, corrosive gases
Overall Size of the Line
56 × 8.5 × 3.5 m (L × W × H)
(Final size subject to detailed engineering design)
Line Division
The whole line is divided into:
• Cell processing section
• Module stacking section
• Module pre/welding/after processing section
• PACK box on-line processing section
• Module into box assembly section
• PACK finished product testing and offline section
Capacity Statement (Investor Standardized Basis)
Based on continuous 3-shift operation (24 hours/day) and 300 operating days per year, the line delivers an annual production capacity of approximately:
1.5 GWh per year per line
This capacity reflects:
• Real-world operating efficiency
• Process synchronization losses
• Maintenance and minor downtime
Line Overall Performance Parameters
SN Item Parameter Description
1 Production Capacity 8 ppm Based on liquid-cooled 1S13P module; excludes manual loading/unloading
2 First Pass Yield ≥98% Based on weld seam
3 Final Yield ≥99.5% Includes rework
4 Failure Rate ≤2% Equipment-only
5 Utilization Rate ≥98% Excludes external downtime
6 Product Changeover ≤4 hours Full line switching
Main Equipment Quotation (SN 1–21)
(Original structure preserved exactly as per quotation)
SN Section Item Amount (USD)
1 Cell Processing Robot Automatic Loading
2 Cell Sorting Sorting System
3 Stacking Automatic Stacking
4 Scanning Binding Station
5 Pressing Online Pressing
6 Module Processing Polarity Detection
7 Laser Cleaning Cleaning System
8 Laser Welding Welding System
9 Module EOL Testing
10 Conveyor Line Double Speed Chain
11 PACK Section Cooling Plate Airtight Test
12 PACK Section Whole PACK Airtight Test
13 PACK Section Code Binding
14 PACK EOL Final Testing
16 Assembly Line Roller Conveyor
17 Control Line Electrical Control
18 Handling Lifter
19 Tooling Fixture Pallet
20 ESOP Electronic Work Instructions
21 Lifting System Crane System